空壓機(jī)的停用在各個單位(wèi)都常有發生。那(nà)麼在初次開機前(qián)空壓機停放時間超過三個(gè)月或空(kōng)壓機停用時間超(chāo)過三個月,再次開機前需要采取有效措施,bi須先請專業空壓(yā)機人員對機器(qì)進行保養檢測,制(zhì)定(dìng)安全措施(shī),避免開機後發生不(bú)良狀況。
The shutdown of air compressors often occurs in various units. Then, before the first start-up, the air compressor parking time is more than three months or the air compressor parking time is more than three months. Before the second start-up, effective measures need to be taken. The Bi must first ask professional air compressor personnel to carry out maintenance and inspection of the machine, and formulate safety measures to avoid adverse conditions after the start-up.
1、先檢查電路狀态,是否正常供電,電壓是否(fǒu)穩定;測量電動機絕緣電阻,數值大(dà)于1MΩ。
1. Check the state of the circuit first, whether the power supply is normal, whether the voltage is stable; Measure the insulation resistance of the motor, the value is greater than 1M.
2、檢查(chá)空壓機配件上是否含有積水,灰塵,及時清理。
2. Check whether there is water and dust on the spare parts of air compressor, and clean them up in time.
3、對進氣口,出氣口全面檢測,防止發(fā)生堵塞現(xiàn)象
3. Overall inspection of intake and outlet to prevent blockage
4、在上(shàng)述都已經(jīng)完成的情況可以接通電源(yuán),查看電腦控制器是否(fǒu)正常運行
4. If all the above have been completed, the power supply can be connected to check whether the computer controller is working properly.
5、更換三濾和潤滑油。因為在長期不用的情況下,三濾,油可能發生(shēng)老化現象,從而造成空壓(yā)機開機運行時間不(bú)長即結膠積碳或堵(dǔ)塞,油路不暢使空壓機主機或其他零部件損(sǔn)壞。
5. Replace three filters and lubricants. Because in the case of long-term non-use, three filters may cause oil aging phenomenon, which causes the air compressor start-up time is not long, that is, cementing carbon deposit or blockage, oil circuit is not smooth, so that air compressor main engine or other parts are damaged.
6、專業人員試機,電路改造後人工(gōng)控制加載卸載,先空載運行10分(fèn)鐘以上,檢測各項指标和(hé)震動、噪音等正(zhèng)常,再進行加載,查看各部件運行正常即可。
6. Professional personnel test machine, after circuit modification, manual control loading and unloading, first no-load operation for more than 10 minutes, detection of various indicators and vibration, noise and other normal, then load, check the normal operation of the components.